HomeNewsSuccess story: The largest Azure migration in Japan

Success story: The largest Azure migration in Japan

This project started from late October 2022 to migrate customer’s (in the beverage industry) systems, with whom we are working as a partner since 2014, from the existing cloud to Azure. On 11th June 2023, the migration of the production environment was successfully on live.
The work was divided into 6 phases and took over 26 hours on weekend from 4 locations: customer site in Tokyo, Suburbs of Tokyo, Tunisia, and Saudi Arabia. After the migration, the system is stable, and end-users are using it without any problems.
This is one of the largest and most successful Azure migration projects not only for Avaxia, but also in Japan.
If your company is interested in Azure migration project, please contact us.

TOP